I-5 North Coast Corridor - Stage 1A |
Description: On Route 5 from San Dieguito River Bridge to San Elijo Lagoon Bridge and on Route 805 from the Carroll Canyon Undercrossing to Route 5. Construct HOV Lanes and other operational Improvements.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego |
City | Encinitas, San Diego, Solana Beach |
Zip Code | 92007, 92014, 92075, 92121, 92130 |
Senate District |
38, 39 |
Assembly District | 74, 75 |
Congressional District | 50, 53 |
Caltrans District |
11 |
County/State Route | San Diego 805 |
Postmile Begin/End | 26.5 28 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 2605 | 1916 |
Lane Miles Added (HOV) | 5.6 | 4 |
Peak Period Time Savings (minutes) | 255739 | 18774 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Arturo Jacobo | (619) 688-6816 | arturo.jacobo@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Arturo Jacobo | (619) 688-6816 | arturo.jacobo@dot.ca.gov | |
Right of Way Phase |
Caltrans | Arturo Jacobo | (619) 688-6816 | arturo.jacobo@dot.ca.gov | |
Construction Phase |
Caltrans | Arturo Jacobo | (619) 688-6816 | arturo.jacobo@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Arturo Jacobo | (619) 688-6816 | arturo.jacobo@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$82,000 | $-57,500 | $24,500 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $57,817 | $57,817 | ||||
Local** |
$20,000 | $30,793 | $50,793 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $102,000 | $31,110 | $133,110 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,000 | $4,972 | $5,972 | $2,344 | |||
Design(PS&E) |
$4,800 | $4,907 | $9,707 | $11,032 | |||
Right of Way |
$8,900 | $-6,300 | $2,600 | $2,824 | |||
Construction |
$87,300 | $27,531 | $114,831 | $117,870 | |||
Total* | $102,000 | $31,110 | $133,110 | $84,873 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
10/30/2005 07/30/2009 |
|
12/19/2005 09/29/2006 |
100 | 12/19/2005 09/29/2006 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/30/2006 10/01/2009 |
|
09/30/2006 04/04/2007 |
100 | 09/30/2006 04/04/2007 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
06/30/2006 10/01/2009 |
|
12/01/2006 12/29/2006 |
100 | 12/01/2006 12/29/2006 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
08/30/2007 06/30/2012 |
|
08/15/2007 07/14/2010 |
0 | 08/15/2007 07/14/2010 |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
01/30/2010 01/30/2014 |
|
06/11/2012 08/28/2014 |
0 | 06/11/2012 08/28/2014 |
0 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 06/30/2008 | 06/30/2008 | 0 | 0 | |||
Implementation Date | 06/30/2008 | 06/30/2008 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 2605 | 1916 |
Lane Miles Added (HOV) | 5.6 | 4 |
Peak Period Time Savings (minutes) | 255739 | 18774 |
Bond Funding Cost | |
---|---|
Adopted: |
$82,000,000 |
Current Approved: |
$24,500,000 |
Actual Expenditures: |
$24,500,000 |
Status as of December 31, 2023.