Caltrans Logo

I-5 North Coast Corridor - Stage 1A

Description: On Route 5 from San Dieguito River Bridge to San Elijo Lagoon Bridge and on Route 805 from the Carroll Canyon Undercrossing to Route 5. Construct HOV Lanes and other operational Improvements.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City Encinitas, San Diego, Solana Beach
Zip Code 92007, 92014, 92075, 92121, 92130
 
Senate District
38, 39
Assembly District 74, 75
Congressional District 50, 53
 
Caltrans District
11
 
 
County/State Route San Diego 805
Postmile Begin/End 26.5 28
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  2605    1916  
Lane Miles Added (HOV)  5.6    4  
Peak Period Time Savings (minutes)  255739    18774  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Arturo Jacobo (619) 688-6816   arturo.jacobo@dot.ca.gov
Design (PS&E) Phase
Caltrans Arturo Jacobo (619) 688-6816   arturo.jacobo@dot.ca.gov
Right of Way Phase
Caltrans Arturo Jacobo (619) 688-6816   arturo.jacobo@dot.ca.gov
Construction Phase
Caltrans Arturo Jacobo (619) 688-6816   arturo.jacobo@dot.ca.gov
 
Corridor System Management Plan
Caltrans Arturo Jacobo (619) 688-6816   arturo.jacobo@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$82,000 $-57,500 $24,500
Non-bond Funding
State/Federal*
$0 $57,817 $57,817
Local**
$20,000 $30,793 $50,793
Non Budgeted ETC
$0 $0 $0
 
Total**** $102,000 $31,110 $133,110

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,000 $4,972 $5,972 $2,344
Design(PS&E)
$4,800 $4,907 $9,707 $11,032
Right of Way
$8,900 $-6,300 $2,600 $2,824
Construction
$87,300 $27,531 $114,831 $117,870
 
Total* $102,000 $31,110 $133,110 $84,873

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/30/2005 

07/30/2009 
 

 
12/19/2005 

09/29/2006 
100  12/19/2005 

09/29/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/30/2006 

10/01/2009 
 

 
09/30/2006 

04/04/2007 
100  09/30/2006 

04/04/2007 


Begin Right of Way Phase

End Right of Way Phase
06/30/2006 

10/01/2009 
 

 
12/01/2006 

12/29/2006 
100  12/01/2006 

12/29/2006 


Begin Construction Phase

End Construction Phase
08/30/2007 

06/30/2012 
 

 
08/15/2007 

07/14/2010 
08/15/2007 

07/14/2010 


Begin Closeout Phase

End Closeout Phase
01/30/2010 

01/30/2014 
 

 
06/11/2012 

08/28/2014 
06/11/2012 

08/28/2014 


Corridor System Management Plan
Adoption Date 06/30/2008    06/30/2008   
Implementation Date 06/30/2008    06/30/2008   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 2605 1916
Lane Miles Added (HOV) 5.6 4
Peak Period Time Savings (minutes) 255739 18774

Bond Funding Cost
Adopted:
$82,000,000
Current Approved:
$24,500,000
Actual Expenditures:
$24,500,000

 

Status as of December 31, 2023.